Futures Forum: Sidmouth Beach Management Plan >>> Pennington Point >>> determining the rate of cliff erosion
This is the latest as outlined in the Herald:
September date for beach plan recommendations
12:30 22 July 2015
Expert recommendations on how to safeguard Sidmouth’s coastline are due in September – but their implementation will be dependent on funding being secured.
East Devon District Council (EDDC) is drawing up a £75,000 beach management plan (BMP) for the town.
In January, the council moved tonnes of shingle to create a ‘winter blanket’. That £100,000 project was carried out using emergency government funding, but the authority has not budgeted to repeat the work this year.
The BMP was hit by delays and EDDC’s accounts show that a £30,000 underspend on it from 2013/14 has been held over to this year.
An EDDC spokeswoman said: “Work on the BMP is continuing to make steady progress and the recommendations from our consultants are due in September.
“However, any future engineering work is dependent on funding from the Environment Agency, Defra and from other sources that we will need to explore, as well as approval from relevant regulators.”
The BMP will look to address issues of coastal erosion, particularly at the east of the River Sid.
A £300,000 project to replace Alma Bridge will not get underway until the plan has been completed.
September date for beach plan recommendations - News - Sidmouth Herald
It is understood that these are the various Stages which the BMP must go through:
Stage 3: review of the final set of baseline reports
Stage 4: a review of the existing Beach Management routine and identification of issues
Stage 5: the drafting of a shortlist of options which have to be reviewed by the Steering Group;
public consultation/stakeholder meeting - to determine what is the preferred option to beach management
Stage 6: the final report to go through Committee and Council;
bid for funding to the Environment Agency
This is the press release from the District Council:
Sidmouth’s coastal defence project moves forward as Beach Management Plan starts to take shape
When this content has been created
22 July 2015Steering Group update reveals considerable progress has been made on BMP
The past four months have been extremely busy for the project team working on the Sidmouth and East Beach Management Plan, as the latest Steering Group newsletter reveals. East Devon District Council’s Assistant Project Manager Tony Burch, has just issued this update, which highlights the positive results that have been achieved in a number of significant areas of the project and outlines the next steps.Coastal process report updated using anecdotal evidence
Thanks to the generosity of Sidmouth’s community - who responded magnificently to the council’s request for more local information to assist with the preparation of the coastal processes report - over 200 photographs, sketches, postcards, timelines, web links and personal memories of the coastline were received at Knowle. This information was passed on to the BMP’s consultants, Halcrow, who at the request of the BMP Steering Group and East Devon, have analysed this important local knowledge and reported their findings in a specific anecdotal evidence section of their revised coastal process report. The report is currently being reviewed by the council and will be released once any changes have been incorporated.Economics baseline report
Now that the Coastal Processes baseline report is nearing completion, work has recommenced on the Economic baseline report and the council is anticipating a draft to be issued for consultation by the end of July. A recent addition to this report has been ‘drive-by’ values of the properties on Cliff Road, which were undertaken by Fulfords, a local estate agency.Aerial survey of Sidmouth shoreline
Hundreds of aerial photographs that were taken by a drone back in March (on behalf of the council) have provided a crucial up-to-date record of the main Sidmouth beach and the cliffs east of the River Sid within the context of the whole coastline from the River Sid to the headland due south of Salcombe Regis. This also means that the council nowhas a record of the main beach just after the shingle recycling project was completed, so any changes can be measured against the photographs produced. Because the images were taken at a lower altitude than historic aerial photographs, there is far more detail in the pictures, including wave patterns around coastal structures, which can be used to assess the cause of erosion.Alma Bridge
Devon County Council (DCC) has drawn up plans to build a clear span bridge (to replace the old Alma Bridge), with its foundations in the cliff face and on the pavement, so it will be less vulnerable to erosion. These plans – which will be undergoing preliminary consultation – will be informed by the revised Coastal Process report.Review of the existing management regime (Stage Three of the BMP)
A review of the existing management regime is now underway, using information from the baseline reports (Stage two of the BMP).The existing management practices are being compared to the issues covered by the coastal processes, coastal defence works, environmental issues, economics reports, to decide whether they are appropriate and this assessment will help inform Stage Four.Development of options for future management regimes (Stage Four of the BMP)
Halcrow have commenced work on the development of potentially viable flood and coastal risk management (FRCM) options ready for the Steering Group to consider in the autumn. This will also include non-FRCM opportunities, based on FRCM actions - for example, if the rock groynes needed to be modified for FRCM reasons, could they be altered to accommodate a passenger dock for the Heritage Coast ferry? The options will be evaluated against technical, environmental and economic criteria to produce a short list on which steering group members and the local community will be consulted, which will in turn be reduced to a final selection of ‘preferred’ options.Railway tunnel
The hunt has been on for the position of the railway tunnel that was excavated in the 19th Century within the cliffs. Although an access adit (entrance) is visible in the cliff face, the BMP project team was keen to pinpoint the rest of the tunnel as it poses a risk of increasing erosion if it collapses. The team believes it found the west and east sections of the tunnel and is currently liaising with the National Trust on what steps to take.Hard work
Commenting on the work that has taken place to date, Councillor Andrew Moulding,East Devon District Council’s deputy leader and Chairman of the Steering Group Committee, said:I would like to thank the project team, Halcrow and the members of the Steering Group for all their hard work and assistance in the development of the BMP. It is tremendously exciting to have reached the fourth stage of this long and technically challenging coastal defence project – we are now only a short step away from being in a position where we can actually start to produce the BMP itself and provide a detailed plan for the short, medium and long-term management of the beach and cliffs.
.
.
.
No comments:
Post a Comment