... A FORUM TO STIMULATE DEBATE ... ... JUST ADD A COMMENT AT ANY ENTRY BELOW... ... FOR THE SUSTAINABLE DEVELOPMENT OF TOWN AND VALLEY ...

Thursday 27 October 2016

Knowle relocation project: BREAKING NEWS >> >>> Information Commissioner tells East Devon District Council to publish documentation

News just in that the ICO have released three Decision Notices. They will be available on their website shortly:

https://search.ico.org.uk/ico/search/decisionnotice

Meanwhile, here is an overview:

Case: FER0626901
Pegasus agreement re Knowle


The ICO are telling EDDC to come up with all of this:

“I would like the Council to disclose the details of the agreement it has entered into with Pegasus for the Knowle site.
I would like to see the full, unredacted version of the agreement.
I understand that the information at issue would not be exploited by a competitor and that disclosure would not place either party at a commercial disadvantage.
All parties, including Pegasus, will have known that they would be subject to the FOIA when the agreement was signed.
To reiterate, I would like the full publication of the commercial terms of the agreement.
I would like you to provide me with all of the documentation I have requested: in their original electronic versions and not in their scanned versions.”


From: 
Pegasus agreement re Knowle - a Freedom of Information request to East Devon District Council - WhatDoTheyKnow


Case: FER0608237
Projected maintenance costs for relocation project


The ICO say EDDC don’t have to produce spreadsheets but have to publish the following re the site at Knowle:

"To disclose the price that the developer is prepared to pay for the land from the cash flow documents which the council withheld."

The ‘Conclusions’ are interesting, however:

"53. There is a public interest in protecting the public purse, in this case this is balanced in this case against the public interest in allowing the public to scrutinise the council’s decisions and financial assumptions about the project to develop new offices for itself. This latter aspect clearly raises the level of transparency which would be expected as the council could be seen to be spending public money on its own facilities, for its own purposes. It has argued that it needs to change offices as overall, doing so would save the public money compared to staying in its current offices. The public however cannot know whether this is true without further information being open for them to scrutinise."

With ref to: 


Case: FER0623403
Decision process which led to the award of the conditional contract with Pegasus re Knowle


The ICO are telling EDDC to come up with the last from this list – EDDC having given the first 5, but not the 6th:

“I request information on the decision to award a contract to PegasusLife for the development of the Knowle site in Sidmouth, including, but not limited to:
1. Bid documentation provided to prospective bidders;
2. process for and criteria for selection of successful bidder;
3. Number of organisations who expressed an interest in bidding;
4. Number of organisations who submitted a bid;
5. Names of organisations who submitted a bid;
6. Minutes of meetings and correspondence on the subject.